Ecobiz.asia — PT PLN (Persero), Indonesia’s state-owned electricity firm, is set to develop approximately 9,000 circuit kilometers (KMS) of new transmission lines across Sulawesi as part of its Electricity Supply Business Plan (RUPTL) 2025–2034.

The expansion is aimed at improving grid reliability and meeting the island’s growing electricity demand.

Andi Murniawati, Senior Manager for Planning at PLN’s Sulawesi Generation and Transmission Unit (UPJB Sulawesi), said the transmission network will be significantly enhanced, with the new lines boosting Sulawesi’s transmission capacity by 1.5 times compared to the current 6,000 KMS.

“This expansion will significantly improve grid performance and help meet Sulawesi’s rising energy needs,” she stated during the Indonesia Sustainable Energy Week 2025 event in Makassar, Thursday (Oct 30, 2025).

Read also:  BRIN, Geo Dipa Develop Modular Wellhead Technology for Small-Scale Geothermal Power

PLN also plans to upgrade substation capacity from 6,600 megavolt amperes (MVA) to nearly 10,000 MVA, in anticipation of an annual electricity demand growth of around 25 terawatt hours (TWh).

The expansion is part of PLN’s strategy to integrate electricity systems across eastern Indonesia, ensuring more robust connectivity and supporting the country’s clean energy transition.

Under the RUPTL 2025–2034, 75 percent of new power plants in Sulawesi will be based on renewable energy and storage, contributing around 8.98 gigawatts (GW). The remaining 25 percent will come from non-renewable sources.

Read also:  Indonesia, South Korea Sign Forestry Deals to Boost Fire Management, Climate Cooperation

Additionally, PLN plans to install Battery Energy Storage Systems (BESS) with a total capacity of nearly 1.6 GW across the northern and southern Sulawesi grids. These systems are expected to stabilize the grid and manage renewable energy fluctuations, such as from solar and wind sources.

Currently, Sulawesi’s power network operates as two separate grids, northern and southern, which are not interconnected. PLN plans to complete the interconnection project by 2028, following the construction of major transmission infrastructure.

Read also:  PLN Indonesia Power Manfaatkan 1,94 Juta Ton FABA Sepanjang 2025

“Once the two systems are connected, we will conduct a system stability study, as linking two large grids over long distances with limited demand in between presents unique challenges,” said Andi.

PLN has also projected demand growth across Sulawesi’s six provinces, with Central Sulawesi, Gorontalo, South Sulawesi, and Southeast Sulawesi expected to experience significant growth, driven by new industrial consumers. North and West Sulawesi, however, are anticipated to see slower demand growth compared to the previous RUPTL period. ***

LATEST STORIES

MORE ARTICLES

Pertamina Strengthens Domestic Bioethanol Development to Support E20 Target

Ecobiz.asia — Pertamina is strengthening the development of domestically sourced bioethanol through cross-sector collaboration to support the country’s E20 blending mandate targeted for 2028. The...

Survey Finds Indonesia’s Renewable Energy Progress Stagnant Despite Strong Industry Demand

Ecobiz.asia — A recent survey conducted by Petromindo Survey highlights growing industry concern over the slow pace of renewable energy development in Indonesia, despite...

PGE Kolaborasi dengan UGM dan PT Agrotekno Estetika Laboratoris Kembangkan Katrili, Inovasi Pertanian Berbasis Geotermal

Ecobiz.asia -- PT Pertamina Geothermal Energy Tbk (PGE) (IDX: PGEO) bersama Fakultas Teknik Universitas Gadjah Mada (FT UGM) dan PT Agrotekno Estetika Laboratoris resmi...

Indonesia Prepares Three Schemes for Biodiversity Credit Implementation

Ecobiz.asia — Indonesia is preparing three key schemes to implement high-integrity biodiversity credits as part of efforts to strengthen biodiversity financing and promote a...

Indonesia Prepares Forestry Carbon Nesting Framework, Riau Selected as Pilot

Ecobiz.asia — Indonesia is preparing to operationalize a forestry carbon nesting framework to support high-integrity transactions and attract global investment into its carbon market. Director...

TOP STORIES

Pertamina Strengthens Domestic Bioethanol Development to Support E20 Target

Ecobiz.asia — Pertamina is strengthening the development of domestically sourced bioethanol through cross-sector collaboration to support the country’s E20 blending mandate targeted for 2028. The...

Kunjungi TPST BLE Banyumas, Presiden Prabowo Soroti Inovasi Sampah Jadi Genteng

Ecobiz.asia — Presiden Prabowo Subianto meninjau Tempat Pengolahan Sampah Terpadu Berwawasan Lingkungan dan Edukasi (TPST BLE) di Banyumas, Jawa Tengah, Selasa (28/4/2026), dan menyoroti...

Survei: Progres Energi Terbarukan Indonesia Stagnan Meski Permintaan Industri Tinggi

Ecobiz.asia — Survei terbaru yang dilakukan Petromindo Survey menunjukkan meningkatnya kekhawatiran pelaku industri terhadap lambatnya perkembangan energi terbarukan di Indonesia, meski permintaan dan ekspektasi...

Survey Finds Indonesia’s Renewable Energy Progress Stagnant Despite Strong Industry Demand

Ecobiz.asia — A recent survey conducted by Petromindo Survey highlights growing industry concern over the slow pace of renewable energy development in Indonesia, despite...

Target Dedieselisasi Dinilai Perlu Diperluas ke PLTU, PLTG

Ecobiz.asia — Rencana pemerintah mengganti 13 Pembangkit Listrik Tenaga Diesel (PLTD) menjadi Pembangkit Listrik Tenaga Surya (PLTS) dinilai perlu diperluas dengan menghentikan pembangunan pembangkit...