GIZ: Indonesia Faces 3.8 GW Annual Renewable Buildout Gap as Procurement Stalls

MORE ARTICLES

Ecobiz.asia – Indonesia needs to accelerate annual renewable power additions by around 3.8 GW to stay on track with its latest electricity supply plan, after new renewable capacity averaged only about 0.4 GW a year between 2021 and 2024, according to GIZ Indonesia.

The average would need to increase to around 4.21 GW annually to deliver the renewable capacity targeted under Indonesia’s 2025-2034 electricity supply plan.

Imam Askolani, Energy Advisor at GIZ Indonesia/ASEAN, presented the assessment during Indonesia Sustainable Energy Week (ISEW) 2026 in Jakarta on Thursday (August 20, 2026).

The 2025-2034 RUPTL calls for 17.1 GW of new solar capacity, 11.7 GW of hydropower, 7.2 GW of wind, 5.2 GW of geothermal and around 0.9 GW of bioenergy. Delivering the pipeline will require Indonesia to move from relatively modest annual additions to several gigawatts of new renewable capacity reaching commercial operation each year.

Read also:  PLN EPI Partners With Chinese Firm to Explore Waste-to-Energy Projects

A GIZ study conducted between October 2024 and August 2025 identified bottlenecks across almost every stage of renewable-energy procurement.

At the prequalification stage, the number of companies included on PLN’s selected-provider list, known as the DPT, has remained limited or stagnant, while relatively few projects have progressed to tender.

Some projects have also stalled before procurement begins. GIZ identified cases where project initiation had not started, prefeasibility studies were delayed, or projects had been initiated but had not progressed to the tender stage.

Read also:  Indonesia Launches SOIFO 2026, Highlights 95.5 Million Hectares of Forest

Delays continue after procurement starts, with the study identifying failed tenders and prolonged or unsuccessful commercial negotiations. These problems can postpone the signing of power purchase agreements (PPAs), further delaying project development.

Even after a PPA is signed, developers can face difficulties reaching financial close, followed by potential delays during construction. GIZ’s findings therefore point to bottlenecks across the entire project-development chain rather than at the tender stage alone.

Solar power illustrates the challenge. GIZ said actual solar PV additions have consistently remained below levels targeted in earlier electricity plans, even as the latest RUPTL significantly increases Indonesia’s solar ambitions.

Read also:  IATA Urges Governments to Strengthen CORSIA as Global Aviation Emissions Scheme Enters Next Phase

The procurement bottlenecks could also affect the government’s broader ambition to develop 100 GW of solar capacity. Meeting that goal would require not only more developers and financing, but also a procurement system capable of moving projects more quickly from prequalification and feasibility studies through tendering, PPA signing, financing and construction.

Indonesia recorded US$2.4 billion (Rp42.8 trillion) in investment realization in new and renewable energy and energy conservation in 2025, while installed renewable generation capacity reached 15.63 GW.

With the latest RUPTL setting a much larger renewable pipeline, the pace at which projects reach commercial operation will increasingly determine whether Indonesia can meet its planned capacity additions. ***

LATEST STORIES

MORE ARTICLES

Beyond the Haze: Why the Singapore-Indonesia Value Chain Demands Real Mutual Accountability

By: Riza Suarga (Chairman Indonesia Carbon Trade Association/IDCTA)  Ecobiz.asia - Singapore’s haze situation has recently been linked by Prime Minister Lawrence Wong to forest and...

Indonesia Targets 2027 Grid Code Revision to Support Renewables, Battery Storage

Ecobiz.asia – Indonesia plans to issue a revised grid code in 2027 to enable greater integration of renewable energy and battery storage while maintaining...

Philippines to Develop National Carbon Market Framework to Attract Investment

Ecobiz.asia – The Philippines will develop a national carbon market policy framework to regulate carbon credit projects and transactions, as the government seeks to...

PLN EPI Partners With Chinese Firm to Explore Waste-to-Energy Projects

Ecobiz.asia – Indonesia’s PT PLN Energi Primer Indonesia (PLN EPI) has partnered with PT Geoenviron Engineering Technology Indonesia (GETI), a subsidiary of China’s Beijing...

Singapore’s First Resources Says Many Fire Hotspots Were Outside Its Operating Areas

Ecobiz.asia – Singapore-listed palm oil producer First Resources Limited says many fire hotspots detected near its concessions in West Kalimantan were outside its operating...

TOP STORIES

Selandia Baru Lanjutkan Program Energi Terbarukan di Maluku, Target Kurangi Ketergantungan Bahan Bakar Fosil

Ecobiz.asia – Program pengembangan energi terbarukan di Provinsi Maluku memasuki fase kedua melalui kemitraan Pemerintah Selandia Baru dan Kementerian Energi dan Sumber Daya Mineral...

Kabar Melegakan! Hotspot Terus Turun Jadi 93 Titik, Kemenhut Pastikan Tetap Siaga Kendalikan Karhutla

Ecobiz.asia — Penurunan jumlah titik panas (hotspot) dengan tingkat kepercayaan tinggi di Indonesia menjadi 93 titik pada Senin (26/10/2026), dari 147 titik sehari sebelumnya,...

PLTS Terapung Karangkates Capai 70% Konstruksi, Bidik Produksi Listrik Perdana Desember

Ecobiz.asia -- PT PLN Nusantara Power (PLN NP) mencatat progres konstruksi infrastruktur Pembangkit Listrik Tenaga Surya (PLTS) Terapung Karangkates di Kabupaten Malang, Jawa Timur,...

Beyond the Haze: Why the Singapore-Indonesia Value Chain Demands Real Mutual Accountability

By: Riza Suarga (Chairman Indonesia Carbon Trade Association/IDCTA)  Ecobiz.asia - Singapore’s haze situation has recently been linked by Prime Minister Lawrence Wong to forest and...

ESDM Bongkar Dugaan Tambang di Kebun Sawit, Sejumlah Perusahaan Asing Didalami

Ecobiz.asia – Kementerian Energi dan Sumber Daya Mineral (ESDM) akan memeriksa sejumlah kebun kelapa sawit yang diduga menjalankan kegiatan pertambangan di luar izin usaha....